What was decided

  • Adopted 2025 Urban Water Management Plan and Water Shortage Contingency Plan [S1]
    • Resolution 3093 (Urban Water Management Plan)
    • Resolution 3094 (Water Shortage Contingency Plan)
    • Plans required by state law, updated every 5 years, due to State Water Resources Department by July 1, 2026
    • City water supply entirely from local groundwater (Kern County sub-basin); seven active wells with two more planned for end of 2027
    • Current well capacity 10,000 gallons per minute (5,300 million gallons per year); will increase to 13,000 gallons per minute (nearly 7,000 million gallons per year) with new wells
    • 2025 demand: 1,400 million gallons; 2050 projected demand: 1,700 million gallons
    • City using approximately 50-60% of available capacity; approximately 3,500 million gallons per year unused
    • Contingency plan has six stages of response; no changes since 2020
  • Approved FY 2026-2027 Operating Budget and Capital Improvement Plan with balanced general fund [S1]
    • Resolution 3085
    • General fund revenues and expenses fully committed with projected small surplus from vacancies and unspent items
    • Water fund: revenues now projected to exceed operating expenses (first time in several years after voter-approved rate increase)
    • Wastewater fund: revenues exceed expenses; rate increases support upcoming capital investments
    • Police department budget increased from $8.1 million (FY 2023) to $15.1 million (proposed)
    • Public works budget increased from $4.2 million to $7.5 million
    • Electricity for water pumping identified as largest single operating cost; solar power purchase agreement subsidizes but does not fully cover pumping costs
  • Adopted disruption policy for city council and commission meetings per Senate Bill 707 [S1]
    • Policy requires 1-hour break if remote access (Zoom, YouTube, telephone) is disrupted
    • Council may meet in closed session during disruption or continue meeting after majority vote finding public interest requires continuation
    • Policy addresses disruptive public participants; allows audio cutoff after warning
    • City already translating agendas and documents; SB 707 now mandates translation across all California cities
  • Awarded Lerdo Highway reconstruction contract (Knight Street to Valley Street) to Bowman Asphalt [S1]
    • Contract amount: up to $1,000,000 for construction
    • Total project budget: $1,015,000 (includes material testing and additional costs)
    • Federally funded project: $750,000 federal funding; local match required
    • Budget amendment: $167,000 gas tax transfer approved
    • Scope: road reconstruction, new ADA curb ramps, sidewalk replacement and installation
    • Three bids received; Bowman Asphalt lowest at $923,955
  • Awarded East Tulare Avenue pedestrian improvements contract (Shafter Avenue to Beach Avenue) to Griffith Company [S1]
    • Contract amount: up to $600,000 for construction
    • Total project budget: $941,000 (fully funded in CIP; no budget amendment needed)
    • Grant funded: $440,000 TDA Article 3 funding
    • Scope: sidewalks, curb and gutter, driveways, ADA curb ramps; continuous sidewalk on both sides from Shafter to Beach Avenue
    • Five bids received; Griffith Company lowest at $517,735
    • Project timeline: 40 calendar days; contractor notified school starts in August and requested to prioritize completion before school year
    • Includes water line installation from school property well to booster station site at Manor Park for future irrigation system
  • Approved consent calendar items including election resolutions and special permits [S1]
    • Resolution 3086: Appropriation limit for FY 2026-2027 per California Constitution Article 13B
    • Resolutions 3087-3089: Called general municipal election for November 3, 2026; requested county consolidation with statewide election; adopted candidate statement regulations
    • Special event permit: Valley Clean Air Now clean green yard machines event June 27, 2026
    • Office furniture purchase: $133,332.27 from Stinson’s for Gossamer Grove Substation
    • Police radio system: $150,000 contingency allocation for bi-directional amplifier and encryption integration
    • Water meter purchase: 253 assemblies from Pace Supply/Badger Meter for $146,366.71
    • Cherry Avenue Grade Separation: authorized mayor to sign funding commitment letter for Federal Railroad Administration CRISI grant application
    • Street striping: approved plans and specifications for 2026 citywide project; authorized formal bidding
    • Sand sealing: accepted bids for oil spreading ($498,397 to Current Asphalt) and oil sand material ($130,000 to Bowman Asphalt)
    • Landscaping and lighting districts: initiated annual levy proceedings and approved engineer’s reports for FY 2026-2027

Who this affects

  • Residents and businesses on East Tulare Avenue and Lerdo Highway: construction during summer months; Tulare Avenue work timed to complete before school starts in August; both projects expected to finish quickly [S1]
  • Water customers: rate increases approved in prior year now generating sufficient revenue to cover operating costs and fund capital improvements (new wells, pumps); no additional rate action needed for FY 2026-2027 [S1]
  • Wastewater customers: sewer rates support upcoming treatment plant capital projects and manhole repair/coating work planned annually [S1]
  • City staff and departments: general fund fully committed; limited discretionary spending; police and public works budgets nearly doubled, reflecting service expansion [S1]
  • Remote meeting participants: Senate Bill 707 compliance ensures translation of agendas and documents; disruption policy clarifies what happens if Zoom/phone access fails [S1]

Perspectives

City staff and council emphasized proactive water planning. Finance Director Roger Sanchez stated the city has been ‘planning for the future’ by drilling wells ahead of demand, contrasting with neighboring Wasco which ’let that slip and they’re way behind.’ Council Member Espinoza noted the importance of transparency: ‘I’d rather tell them, “Hey, we have these projects coming up,” from ahead of the curve instead of behind the curve.’ Jake Colmer (Weston Associates) confirmed water supply capacity is ‘sufficient to meet demands even under drought conditions up through 2050.’ [S1]

Sources

  1. S1 — Video (transcript)

People and organizations

WaterBudgetUtilitiesTransportationProcurementPublic-SafetyEnvironment

Written by claude-haiku-4-5 on August 1, 2026 from the sources above. Not reviewed by a person.