Wasco City Council — July 7, 2026

City Council – July 7, 2026 · Tuesday, July 7, 2026 · Preview

Staff will give an informational update on Wasco's road, bike lane, traffic signal and streetlight projects. No vote is listed. Two crossing signal projects are delayed while new pole delivery dates are set.

What’s proposed

  • Proposed: Staff status update on the Capital Improvement Program (CIP), for information only [S1]
    • The city’s Engineering Department will report on active projects as of July 6, 2026.
  • Two crossing signal projects are delayed while new pole deliveries are scheduled [S1]
    • A pedestrian crossing signal (called a HAWK) at Poplar Avenue and Highway 46, funded through the Highway Safety Improvement Program (HSIP).
    • Rectangular flashing beacons at 8th Street and Highway 43, also HSIP-funded.
    • Staff is working with the contractor and supplier to set new delivery and installation dates for both.
  • Road and bike lane work moves toward bidding and construction [S1]
    • Beckes Road rehabilitation from 5th Street to Highway 46: bids opened July 2. Staff expects council award July 21, with construction in mid-August.
    • Alley reconstruction in the Filburn Avenue and 16th Street area, funded by REAP 2.0 (the state Regional Early Action Planning 2.0 program): bids opened July 2. Staff expects council award July 21, with construction in mid-August.
    • Filburn Avenue shoulders from Central Avenue to Palm Avenue and from Griffith Street to G Street, funded by Congestion Mitigation and Air Quality (CMAQ) funds: Caltrans authorized funding July 3. Bid packages are being assembled.
    • Filburn Avenue road rehabilitation from Central Avenue to G Street, funded by the Regional Surface Transportation Program (RSTP): bid package being prepared to advertise with the shoulder work.
    • Central Avenue bike lane project from Poso Avenue to Flower Street, funded by the Active Transportation Program (ATP): design 95% complete, pending landscape revisions. Construction expected September.
  • Road surfacing and striping bids open July 7 [S1]
    • NE Zone pavement maintenance: fiberized slurry seal (a thin protective road coat) on roads bounded by 5th Street, Highway 46, Griffith Avenue and Highway 43. Funded by SB1 (Senate Bill 1, state road repair funds).
    • Citywide striping: re-striping of centerlines, bike lanes, fog lines and turn lanes, funded with local city funds.
  • G Street lighting work nears electrical connections [S1]
    • City crews have placed all but three lights. Staff expects all lights in place by the end of this week.
    • Electrical tie-ins (wiring connections) are expected to begin July 20. Funded with local funds.
  • Council reports on regional transportation meetings [S1]
    • Acting Mayor Reyna will report on the June 18 update from the Kern Council of Governments and the June 18 meeting of the Transportation Planning Policy Committee.

Who this affects

  • Pedestrians and drivers at Poplar Avenue and Highway 46, and at 8th Street and Highway 43: the new crossing signals will arrive later than first scheduled. [S1]
  • Residents and drivers near Beckes Road and the Filburn Avenue and 16th Street alley area: road and alley construction equipment and work zones once construction starts. [S1]
  • Drivers and shoulder users on Filburn Avenue: wider shoulders and road repairs. [S1]
  • Cyclists, pedestrians and nearby residents on Central Avenue from Poso Avenue to Flower Street: new bike lanes, sidewalks and landscaping. [S1]
  • Residents and drivers citywide and in the NE Zone: new road surface coat and fresh lane lines once the work is done. [S1]
  • Residents on G Street from 6th Street to Filburn Avenue: street lighting work and electrical connections. [S1]
  • Paving and striping contractors: bid openings on July 7 determine who may be selected for the work. [S1]

Perspectives

The record for this item is a staff status report. It shows no public comment or council debate, so no disagreement can be reported. [S1]

Sources

  1. S1 — Materiales suplementarios de la agenda de los puntos 14c y 17 de reunión regular del Ayuntamiento 7 de julio de 2026 (agenda)

People and organizations

TransportationPublic-SafetyProcurementUtilities Capital Improvement ProgramPoplar Avenue HAWK Pedestrian Signal (HSIP)8th Street Crosswalk Enhancements (HSIP)Beckes Road RehabilitationREAP 2.0 Alley ReconstructionsFilburn Avenue Shoulder and Road Rehabilitation ProjectsCentral Avenue ATP Bike Lane ProjectG Street LightingNE Zone Pavement MaintenanceCitywide Striping Project

Written by anthropic/claude-haiku-5.5 on October 21, 2026 from the sources above. Not reviewed by a person.